When Will Work on the Water Project Be Happening On My Street?

The projected work schedule for the phase 3 water system improvement project in Hamilton, which will run from August through December 2017 with final paving in May 2018. All dates are subject to change

Lincoln Avenue: Aug. 14 – Sept. 11, 2017

Union Street: Aug. 14 – Sept. 18, 2017

Day Avenue: Aug. 30 – Sept. 18, 2017

Lorenzo Street: Sept. 8 – Sept. 20, 2017

Western Avenue: Sept. 12 – Sept. 28, 2017

Willow Street: Sept. 15 – Oct. 12, 2017

Roosevelt Avenue: Sept. 22 – Oct. 2, 2017

Central Avenue: Sept. 29 – Oct. 11, 2017

Cummings Avenue: Oct. 3 – Oct. 20, 2017

Moynihan Road: Oct. 3 – Nov. 1, 2017

Railroad Avenue: Oct. 5 – Nov. 3, 2017

Pleasant Street: Oct. 11 – Nov. 13, 2017

Elliot Street: Oct. 13 – Nov. 20, 2017

Home Street: Oct. 17 – Dec. 1, 2017

Honeysuckle Road: Oct. 18 – Nov. 20, 2017

Naples Road: Oct. 23 – Dec. 15, 2017

Red Coach Road: Oct. 26 – Dec. 4, 2017

Savoy Road: Oct. 26 – Dec. 27, 2017

Howard Street: Nov. 1 – Nov. 9, 2017

Madonna Drive: Nov. 2 – Dec. 15, 2017

Lois Street: Nov. 13 – Nov. 21, 2017

Essex Street: Nov. 22 – Dec. 19, 2017

Anthony Road: Dec. 8 – Dec. 27, 2017

Chebacco Road: Dec. 20, 2017 – Jan. 2, 2018

Final road paving for entire project: May, 7 – May, 25, 2018

Advertisements

One thought on “When Will Work on the Water Project Be Happening On My Street?

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s